Project: NCB EASTERN REGION CORPORATE BUILDING Al-KHOBAR – KSA
Location : Al Khobar
Main Contractor : Al Taafuf Co for Electrical Works Jeddah, Saudi Arabia
STS Scope : Civil and Architectural works, Electrical and Mechanical Works
Contract Value : SR 110M
Estimated Commencement : 01 June 2019
Estimated Completion : 31 May 2021
STS Scope
STS is contracted to execute the Civil, Electrical and Mechanical Works and power connection for the entire project in accordance with the specifications and standards mentioned in the Main Contract. The works include employ and supervise the necessary manpower, provide all materials, services tools & equipment necessary to carrying out the required work, and to provide for co-ordination with other trades where needed, under this subcontract. The works covers excavation, concrete works, block and plastering works, wood, tiles, false ceiling aluminum, finishing and painting works, engineering, shop drawings, supply and installation of all electrical and mechanical works including; medium voltage distribution network, low voltage network, elevators, chilled water system, fire fighting, plumbing works and fire alarm system.
STS is contracted to execute the Civil, Electrical and Mechanical Works and power connection for the entire project in accordance with the specifications and standards mentioned in the Main Contract. The works include employ and supervise the necessary manpower, provide all materials, services tools & equipment necessary to carrying out the required work, and to provide for co-ordination with other trades where needed, under this subcontract. The works covers excavation, concrete works, block and plastering works, wood, tiles, false ceiling aluminum, finishing and painting works, engineering, shop drawings, supply and installation of all electrical and mechanical works including; medium voltage distribution network, low voltage network, elevators, chilled water system, fire fighting, plumbing works and fire alarm system.